As an operator of a combustion plant (medium-sized combustion plant, gas turbine plant and internal combustion engine plant) with a rated thermal input of at least 1 MW and less than 50 MW, you are required to notify the competent authority in writing or electronically of the intended operation before commissioning. The operation of an existing combustion plant must be notified in writing or electronically to the competent authority by December 1, 2023. The notification must contain the information specified in Annex 1 of the 44th BImSchV. The competent authority shall record the plant in its plant register. You will be informed about the registration by the competent authority.
Process flow
The notification must be submitted in writing by mail or electronically to the competent authority.
Who should I contact?
Please contact the responsible district office, the independent city or the Thuringian State Office for the Environment, Mining and Nature Conservation (TLUBN).
Which documents are required?
Display with the data relevant to the plant:
- Combustion heat output of the firing plant (in megawatts);
- Type of combustion plant (diesel engine plant, gas turbine, dual-fuel engine plant, other engine plant, other combustion plant);
- Type of fuels used and respective share of total energy input;
- the date of commissioning of the combustion plant;
- the NACE code to which the other activity is to be assigned,
- expected number of annual operating hours of the combustion plant and average operating load;
- if a scheme for plants with few operating hours is used: a statement signed by the operator that the combustion plant will not be in operation for more than the number of hours specified in those paragraphs;
- if an emergency operation scheme is used: a statement signed by the operator that the combustion plant will be in operation only in case of emergency;
- Name and place of business of the operator and location of the plant with address;
- Geo-coordinates of the chimney and height above ground.
What are the fees?
There are no costs involved.
What deadlines do I have to pay attention to?
The notification must be submitted before commissioning a new plant. The operation of an existing plant must be notified by December 1, 2023.
Legal basis
Applications / forms
This administrative service does not constitute an administrative act. For this reason, no legal remedy results.
Author
The text was automatically translated based on the German content.
Technically approved by
Thuringian Ministry for the Environment, Energy and Nature Conservation
Professionally released on
01.07.2022
Source: Zuständigkeitsfinder Thüringen (Linie6PLus)
No competent authority found
Please enter your location.