Registering electricity and gas units in the register
Service Description
As the central register for the energy transition, the Market Master Data Register (MaStR) records data on all generation plants:
- All new plants and all existing plants,
- installations for the generation of renewable and conventional energy,
- electricity and gas generation plants.
If you operate an electricity or gas generation plant (for example, photovoltaic plant, wind energy plant, combined heat and power plant, battery storage, biomethane plant), you must register it in the MaStR. You are also obliged to register if no subsidy is granted or claimed for the electricity from the plant.
All running plants must be registered regardless of when they were commissioned - even if your plant has been running for many years. This means that even if you have already registered your plant in various other places, for example with your grid operator or in earlier registers of the Federal Network Agency, you must register these plants again in the MaStR.
If an installation is shut down, you must also report this in the register. If the installation is not connected to any electricity or gas grid, no notification is required.
To ensure that payments under the Renewable Energy Sources Act (EEG) or the Combined Heat and Power Act (KWKG) are paid out without deductions, you must comply with the registration deadlines set by the legislator.
You must register via the Federal Network Agency's Internet portal.
As a citizen, you can also register via forms in exceptional cases.
Authorities can access the MaStR data. This enables them to either significantly simplify their own surveys or dispense with them altogether. Plant operators and other market players can refer to the data they have entered in the MaStR.
Process flow
If you would like to register yourself as an operator and your electricity and gas generation plants in the MaStR, you can do so via the MaStR Internet portal:
- Access the MaStR Internet portal and first register as a user with a valid e-mail address.
- Log on to the MaStR Internet portal and register as an installation operator.
- Then register your installations.
- If your registration is successful, the system will provide you with your registration certificate with your registration numbers (MaStR numbers).
- You can make changes and corrections online at any time.
Requirements
You do not have to meet any prerequisites.
Which documents are required?
The information required for registration can be found in the following documents:
- Commissioning record of the electricity or gas generation plant.
- Year-end accounts
- previous registration certificates from the Federal Network Agency
What are the fees?
You don't have to pay anything.
What deadlines do I have to pay attention to?
You must register within 1 month of the occurrence of an event requiring registration.
Processing duration
- Online procedure: none, registration confirmation can be printed out directly
- Form registration: approx. 14 days (from application to receipt of registration confirmation)
Legal basis
Applications / forms
There is no provision for appeal.
Appeal
Forms: in exceptional cases only for natural persons on request (by telephone or in writing)
Online procedure: yes
Written form required: no
Personal appearance required: no
Further Information
Author
- Marktstammdatenregister Strom und Gas Registrierung von Einheiten und von EEG- und KWK-Anlagen
Remark: Anzeige der Leistung im Ursprungsportal
Technically approved by
Federal Ministry for Economic Affairs and Energy
Source: Zuständigkeitsfinder Thüringen (Linie6PLus)
Start your request directly online:
Competent Authority
Bundesnetzagentur für Elektrizität, Gas, Telekommunikation, Post und Eisenbahnen (BNetzA)
Address
53113 Bonn, Stadt
Postal address
53105 Bonn, Stadt
Further Authorities
Address
53113 Bonn, Stadt