Service Description
If you wish to make a change to the location, nature or operation of an installation that requires a permit, you must notify the competent authority before starting the change.
The competent authority will confirm your notification and decide whether your project requires a permit and/or which documents you may need to submit. This also applies to accident-relevant changes or if you intend to cease operations.
Process flow
Changes to the location, type or operation of an installation requiring a permit must be notified to the competent authority in writing or electronically at least one month before the change is to begin, unless a permit is applied for.
- You must notify the competent authority of the planned change in writing or, if necessary, using the ELiA web application.
- You enclose the necessary documents with the notification, insofar as these may be required to check whether the project requires approval.
- The competent authority will immediately confirm receipt of the notification and the enclosed documents in writing or electronically; in the case of an electronic notification, it may also request additional copies and the transmission of the documents to be enclosed with the notification in written form.
- Upon receipt of the notification, the competent authority will inform you immediately which additional documents it requires to assess the requirements.
- If necessary, the competent authority will decide that your project requires a permit. The authority will inform you of its decision within one month
- You may implement the change as soon as the competent authority informs you that the change does not require approval or the competent authority has not issued a statement one month after the notification documents are complete.
- In the case of an incident-relevant change, you may only make the change if the competent authority informs you that no approval is required.
Who should I contact?
Please contact the immission control licensing authorities in Thuringia: Thuringian State Office for the Environment, Mining and Nature Conservation (TLUBN) or the districts and independent cities.
Competent authority
The responsible authorities are the immission control licensing authorities of the state of Thuringia in the form of the Thuringian State Office for the Environment, Mining and Nature Conservation (TLUBN) and the lower immission control authorities of the districts and independent cities.
Requirements
- You must enclose the necessary documents with the notification, insofar as these may be required to check whether the project requires approval.
- If, in the opinion of the competent authority, approval is required, an approval procedure must be carried out.
- Approval is not required if the adverse effects caused by the change are obviously minor.
Which documents are required?
The notification procedure requires a written or electronic notification. The following documents must be enclosed:
- Required drawings, plans, expert opinions
- explanations and
- other documents (if necessary, ask the competent authority).
What deadlines do I have to pay attention to?
Application Deadline: 1 MonthBefore implementation of the amendment
Processing duration
Processing Time: 1 MonthIn the event of an incident-relevant change, processing takes 2 months.
Applications / forms
- Objection
- Complaint
What else should I know?
Notification is only required if the change may have an impact on protected assets.
Author
The text was automatically translated based on the German content.
Technically approved by
Thuringian State Office for the Environment, Mining and Nature Conservation
Professionally released on
19.06.2024
Source: Zuständigkeitsfinder Thüringen (Linie6Plus)
Competent Authority
Landeshauptstadt Erfurt, Stadtverwaltung - Immissionsschutz/Chemikalienrecht
Address
99085 Erfurt
Address
Opening times
Tuesday 09:00 - 12:00 and 13:00 - 18:00
Friday 09:00 - 12:00
Transport connection
Further Authorities
Address
99423 Weimar