Service Finder
Show installation and decommissioning of publicly accessible charging points
Service Description
You must notify the Federal Network Agency (BNetzA) of charging points if you
- set up or decommission publicly accessible normal and fast charging points for electric vehicles with a charging capacity of more than 3.7 kilowatts.
- make private charging points public or hand over your publicly accessible charging points to another operator.
The obligation to notify applies to all normal charging points that were put into operation after 17.03.2016 and to all fast charging points.
- Normal charging points have a maximum charging capacity of 22 kilowatts.
- Fast charging points have a charging capacity of more than 22 kilowatts.
-
A charging point is publicly accessible if it is located either on a public road or on private land and the parking space belonging to the charging point can be used by anyone.
Process flow
You can submit the notification using an online form.
Notification of installation or decommissioning via an online form:
- Go to the website of the Federal Network Agency and open the online form.
-
Complete the online form and upload the required documents.
- You can also submit the additional documents by e-mail or post.
- Submit the form electronically.
- The Federal Network Agency will check your notification.
- You will receive written information with your data entry and, if applicable, an operator number by e-mail.
- The Federal Network Agency will publish the charging points on its website if the notification is complete and you have consented to publication.
Notification of a change of operator:
- On the website of the Federal Network Agency you will find a "Form: Change of operator".
- Complete the form and send it by e-mail to the Federal Network Agency's charging point ordinance mailbox.
- The Federal Network Agency will confirm receipt and processing of the information by e-mail.
Requirements
You are planning to install a publicly accessible charging point or are already operating publicly accessible normal or fast charging points.
Which documents are required?
Operators of fast-charging points must also provide evidence of compliance with the technical requirements of the ordinance by enclosing a commissioning report signed by a qualified electrician.
What are the fees?
There are no costs for you.
What deadlines do I have to pay attention to?
You must submit notification of the installation at least 4 weeks before the planned start of the installation of charging points.
You must report the decommissioning of charging points immediately.
Processing duration
The notification is usually processed after 2 to 3 weeks.
Applications / forms
As this is a notification procedure, no administrative decisions are made against which an appeal could be lodged.
Appeal
- Forms: yes
- Online procedure possible: yes
- Written form required: no
- Personal appearance required: no
Further Information
Author
The text was automatically translated based on the German content.
- Display for setting up and decommissioning charging points Acceptance
Remark: Display of performance in the source portal
Technically approved by
Federal Ministry for Economic Affairs and Energy
Professionally released on
07.09.2021
Source: Zuständigkeitsfinder Thüringen (Linie6PLus)
Competent Authority
Bundesnetzagentur – Referat 620 – Ladepunktanzeige
Address
53113 Bonn, Stadt