Sidewalk crossings, or also called property driveways or curb drops, are used to provide easy vehicle access to a property from the street.
If you are planning such a project that requires lowering the curb, you will need a sidewalk crossing permit.
Existing sidewalk crossings can also be modified.
You can apply to modify a sidewalk crossing.
Property driveways require a different design or paving than the sidewalk. That is why these measures must be approved by the responsible body.
It does not matter whether the work involves the construction or modification of a sidewalk crossing.
As a rule, the work in the public road space is commissioned by the city. In exceptional cases, you as the applicant may commission the work yourself from an approved specialist company.
Process flow
As soon as the application has been submitted, it will be checked whether there are any reasons against the execution of the sidewalk crossing.
After your application has been reviewed, you will receive a notice of approval or denial.
Who should I contact?
You can apply for a change of a road crossing in the relevant office of your city or municipality.
Requirements
You yourself are the owner of the property.
Alternatively, you have a power of attorney from the property owner.
If you are allowed to carry out the construction yourself, the company commissioned must be an approved company.
The height and visual continuity of the sidewalk must be maintained.
There must be no interruptions to the sidewalk as a result of the measure.
What are the fees?
In addition to the administrative fee, there are production costs for the modification of the sidewalk crossing.
The fee and production costs depend on the size and nature of the sidewalk crossing.
For example, there may also be costs for tree replacement plantings or light pole relocations.
Both cost components must be borne by the person making the request.
What deadlines do I have to pay attention to?
none
Processing duration
The processing time distinguishes application processing and change of sidewalk crossing.
The application processing is immediate.
The change of the sidewalk crossing by the competent body: At least 3 months.
Applications / forms
Appeal
For more information on how to file an appeal, please refer to the decision on your application
Action before the administrative court
Appeal
Please contact the relevant office in your city or municipality.
What else should I know?
Comments
Only the change is requested, the previous permission of a sidewalk crossing is still valid.
The sidewalk crossing may not be changed itself, for example with wooden beams, steel ramps or similar. This is an unauthorized encroachment into the road space and may be punishable by law.
The permission to change a sidewalk crossing does not replace other required official permits or result in claims from it, for example, for the construction of a garage or a carport.
Author
The text was automatically translated based on the German content.
Technically approved by
Thuringian Ministry for Infrastructure and Agriculture
Professionally released on
05.10.2022
Source: Zuständigkeitsfinder Thüringen (Linie6Plus)
No competent authority found
Please enter your location.